Phase 2
Phase 2 of the Programme is now underway, with 27 projects approved across County Meath to a total value of €910,459.72. All projects have completed the mobilisation stage, with signed Memoranda of Understanding in place and project delivery commenced from 10th June 2026.
Projects are progressing in line with agreed timelines and programme requirements, with completion scheduled by 27th October 2027. Ongoing monitoring and support will continue to ensure successful delivery and achievement of programme objectives.
Programme Milestones
1. Programme Launch: Applications opened on 13th October 2025. Information sessions and engagement meetings with community groups were delivered in August 2025.
2. Application and Assessment Stage: The application period closed on 9th December 2025, with 75 applications received. A joint evaluation process by Meath County Council and the Department of Climate, Energy and the Environment was undertaken from December 2025 to May 2026, resulting in 27 projects approved, with a total allocation of €910,459.72.
3. Notification and Communications: Applicant community groups were notified of outcomes on 27th May 2026. Communications also issued to elected members, and queries from unsuccessful applicants were addressed.
4. Project Mobilisation: Signed Memoranda of Understanding (MoUs), including agreed deliverables and milestones, were returned by 10th June 2026, with project start dates commencing from 10th June 2026.
5. Project Delivery: All projects are scheduled for completion by 27th October 2027.